RFP target · Kickoff week of October 5 · Launch January–February

A sequence that fits the window.

Exact dates confirm at kickoff. Parallel workstreams (IAWF content gathering, third-party integrations) sit off the critical path.

  1. 01

    Discovery & IA

    Oct 5 – Oct 24 · 2–3 weeks

    Kickoff, stakeholder sessions, audit, sitemap, user journeys, wireframes, accessibility and multilingual recommendations

  2. 02

    Design System & Templates

    Oct 27 – Nov 21 · 3–4 weeks

    Visual design system, main page templates, event microsite template library, responsive review, client feedback rounds

  3. 03

    Development

    Nov 24 – Jan 16 · 7–9 weeks

    Divi Theme Builder templates, core pages, event framework (Multisite or CPT + ACF plugin), integrations, SEO/analytics foundation

  4. 04

    Content Migration & QA

    Jan 12 – Jan 30 · 2–3 weeks

    Migration of prioritized content, redirects, accessibility testing, cross-browser/device QA, security review

  5. 05

    Training, Docs & Launch

    Feb 2 – Feb 20 · 2 weeks + support

    Staff training, documentation handover, final content polish, soft launch, go-live support, post-launch monitoring